Private companies now carry out almost all our renewable energy projects and run more than half of power distribution, Electricity and Renewable Energy Minister Mahmoud Esmat said at the British Egyptian Business Association (BEBA) panel on 19 November, which EnterpriseAM attended. The state, however, is keeping the grid and the final say on prices.

What the private sector is building

The private pipeline is large. Some 30 GW of solar and wind projects, plus storage, are underway, with the private sector carrying nearly USD 30 bn in expected investment, Esmat said. Those projects are moving ahead “even with the government currently stepping back,” he told the panel, pointing to Alcazar Energy’s USD 420 mn agreement for the Gabal El Zeit wind farm as an example.

The government also wants that capacity sooner. It now aims to generate 45% of our power from renewables by 2028, up from a previous target of 42% by 2030, with 10.5 GW of renewable capacity already on the grid, according to a ministry statement.

Thermal plants will carry most of the load for some time yet. They still supply around 75% of generation, Esmat said, after electricity demand grew 7% this summer and peak load topped 40 GW. Keeping up could take around 15 GW of new thermal capacity alongside renewables, he said. For those plants, the government is open to 20-year build-operate-transfer contracts.

What the state is keeping

Private distribution already runs in compounds and new cities. The state installs a single high-voltage meter at each site, leaving the developer to distribute power from there, Esmat said. Three or four projects are ready to generate power off-grid or run networks in areas they could take over, he added, without naming them.

The ministry is wary of going much further. It remains cautious about extending distribution license terms, Esmat said, and he has reservations about a model of many small licenses, which could number around 2k. He would rather see larger operators covering a whole governorate or several. A single company could serve around 150k subscribers in Port Said or Ismailia, he said.

The grid itself stays public. “The grid operator will not change, and there is no intention to change it,” Esmat said. Private companies can build substations to the state’s specifications, but the state will operate and maintain them.

So do prices. The government has chosen to keep subsidizing electricity, giving priority to industries that bring in new technology or capabilities, Esmat said. Power plants pay around USD 4 per mmBtu for gas whose actual cost can reach USD 25-26, with the petroleum sector covering the difference, he added. Private distribution complicates that picture. If end-user prices rise while the high-voltage tariff that distributors pay the state stays fixed, the entire gain could go to the distributors, which calls for “a delicate balance,” he said.

The state is also footing most of the bill for the build-out. Esmat’s presentation puts EGP 4.964 tn toward current and future power projects under targets running to 2028 and 2040. Generation takes the largest share at EGP 2.583 tn across renewables and thermal, followed by EGP 1.625 tn for the El Dabaa nuclear plant, EGP 646 bn for transmission, and EGP 110 bn for distribution. The Egyptian Electricity Transmission Company has spent around EGP 160 bn on the development projects so far, Esmat said.

Solar’s next phase

Local manufacturing has started: Egypt now has two or three solar panel factories, and a battery factory and a wind turbine factory are on the way, Esmat said. Amea Power signed contracts this month for one such factory, a USD 200 mn plant with China’s Mingyang Smart Energy. For solar, turning quartz into silicon ingots and wafers still happens abroad, our August reporting found.

Rooftop owners can sell surplus power to the grid again. The ministry suspended the net-metering system for three or four months last year and reinstated it in February, Esmat said in reply to panel moderator and Orascom Construction’s Vice President of Business Development Tamer Shafik. Solar firms pushed back hard while it was suspended. The only obstacle left is “a purely technical matter,” covering harmonics, transformer loads, and inverter types, he said.

The terms come from the electricity regulator’s February circular (pdf). It targets 1 GW of net-metered solar by 2030, including capacity installed before the circular, and requires local content of at least 25% in each plant’s components.

Factories have their own program on top of that. The government’s 1 GW Shams El Sinaa initiative targets around 7k facilities, roughly 10% of our licensed industrial base, at an average of 150 kW each, with Central Bank of Egypt financing at an interest rate of 6-7% or less, Esmat said. Industry had pushed for a bigger program. In May, the Sustainable Energy Development Association and the Cairo Chamber of Commerce’s sustainable energy division called for a 5 GW target and for each factory’s capacity to reflect its own needs rather than a 150 kW standard, according to a statement (pdf). The terms the Cabinet approved on 28 October sort projects by size, with a fast track for plants of up to 499 kW and a second track for larger ones.