Posted inEnergy

Green hydrogen pipeline narrows to a handful of projects as 20 companies step back

The projects still moving generate their own power or start small, while an MP wants future extensions tied to binding milestones

Our green hydrogen pipeline has thinned to a handful of projects after 20 companies stepped back from their agreements with the government. In a written reply to MP Yasser El Hudaibi, published by Attaqa last week, the Electricity Ministry listed the companies that have withdrawn, stalled, or let their agreements lapse. The ministry blamed slowing European demand, a shortage of long-term offtake contracts, and high production and financing costs. The cost of carrying renewable power to the hydrogen cluster at Sokhna weighed on many developers too, Hydrogen Intelligence founder Osama Fawzy tells EnterpriseAM.

The list reads like a roll call of the companies behind our headline figures from 2022 and 2024. By our count, seven of the nine framework agreements signed at COP27, worth up to USD 83 bn, are on it. So are all seven companies from the USD 41 bn MoU round in February 2024.

The exits range from formal withdrawals to lapsed MoUs, according to the ministry’s reply. Fortescue and Globeleq asked to end their framework agreements, while Maersk formally apologized for not continuing. The Total-Enara consortium missed the deadline for its pre-feasibility study. Alfanar, China Energy, Amea Power, ReNew Power, the Taqa-Voltalia consortium, Germany’s DAI, and the Masdar-Infinity-Hassan Allam Utilities-BP consortium have not completed implementation. Neither has Scatec, though it remains part of the Egypt Green project. The other eight let their MoUs expire without submitting the required studies, all but one of them from the February 2024 round.

Developers have also delayed or withdrawn from projects in Oman, Europe, and Southeast Asia over geopolitical uncertainty, Fawzy says. “We shouldn’t present Egypt as the only country developers have withdrawn from,” he adds.

Costly lines, cautious buyers

Getting renewable power to Sokhna came with a bill that sent some developers home. State grid operator EETC set a high wheeling tariff, the fee for carrying privately generated electricity over the national grid, on deliveries to the hydrogen cluster northwest of Sokhna port, Fawzy says. From Benban, that’s an 800-900 km trip. The state then gave developers the option of building their own lines, at their own cost, from wind and solar sites at Ras Gharib, Ras Shokeir, and Zafarana, 80-200 km away. For some of those with wind and solar assets, selling power to EETC offered better returns than a USD 4-5 bn hydrogen project, he says.

On the other side of the table, buyers are holding off. The EU added only 308 MW of electrolyzers in 2024, about 7.7% of its 6 GW annual target, while new global offtake agreements fell to 1.7 mn tons a year in 2024 from 2.4 mn tons in 2023, the ministry said. Unsubsidized green hydrogen still costs EUR 4-7 a kg in most of Europe, against EUR 1.5-2.5 for grey hydrogen made from natural gas, according to its reply. Buyers expect the cost of green hydrogen to keep falling and are reluctant to commit now, Fawzy says. Offtakers also want projects to hit development milestones before they sign, Hussein Rihan, Ocior Energy Holdings’ business head in Egypt, tells EnterpriseAM. Without offtake for most of its capacity, no project can reach a final investment decision (FID), he says.

A handful of projects are still moving

Egypt Green is the furthest along. The Sovereign Fund of Egypt signed the project agreement for the 100 MW plant with Scatec, Fertiglobe, and Orascom Construction in July 2024, with Fertiglobe committed to buying its entire green ammonia output for 20 years. The project’s first phase is running and has begun exporting to European and US markets, the ministry told the House, with FID on full capacity expected in 2027 or 2028. Fawzy gives a more cautious timeline: the pilot inaugurated at COP27 has run at 5-10 MW of its 15 MW, and production from 100 MW of electrolyzers, the units that split water into hydrogen, should start around the turn of the year, with another 100 MW in 2028, he says. Fertiglobe also holds a EUR 397 mn contract to supply green ammonia to the EU through Germany’s H2Global import scheme, we reported.

EDF-Zero Waste plans to make its own power, and Fawzy expects Acwa to follow. EDF and Zero Waste will produce hydrogen and ammonia right beside their wind and solar plants at Ras Shokeir, with 10-15 km of lines and their own Red Sea jetty, Fawzy says. The consortium has reached final feasibility studies and is due to announce financial close in mid-2027, he adds. At its latest meeting, the National Green Hydrogen Council gave Acwa’s East Nile project, which would produce 66k tons of green hydrogen and 500k tons of green ammonia, a one-year extension to its land MoU, the Cabinet said. Fawzy expects Acwa to build out its wind and solar projects first and dedicate part of the output to hydrogen.

Ocior has secured land approval for a solar plant and will build its own line to Sokhna. The council also approved a request by India’s Ocior to designate 12 sq km in West Zafarana for a 600 MW solar plant, which will feed the 100k ton-a-year pilot phase of a green ammonia project with a total annual capacity of 1 mn tons, built in phases, the Cabinet said. Ocior will run its own line from the plant to its ammonia facility at Ain Sokhna and will settle the final solar and battery mix once the land coordinates are defined, Rihan says.

Strings attached?

MP Marwa Borais wants future extensions tied to firm commitments. “The Electricity Ministry’s response confirms what we raised in the briefing request about the gap between announced investments and actual implementation, but it did not clarify the volume of investments realized or the economic returns compared with targets,” Borais tells EnterpriseAM. She wants any extension tied to a binding timeline, completed feasibility studies, long-term offtake agreements, and proof of financing. “MoUs should not become a way to hold onto national land and resources without actual investment,” she says.

Fawzy proposes similar milestones and a smaller starting point. Developers would first deliver a techno-economic feasibility study, agreements with electrolyzer suppliers, funding, and front-end engineering design. After that would come a final agreement with the state giving developers 36-45 months to build. He also proposes small modular plants of 20-50k tons a year as a proof of concept, with the state as a local buyer.