Egypt has many of the ingredients needed to become a regional AI infrastructure hub — but turning those advantages into bankable projects is another matter. Strategic location, submarine cable connectivity, relatively competitive construction costs, and renewable energy potential all work in Egypt’s favor. Yet developers still face a fundamental challenge: How do you secure customers for infrastructure that hasn't been built, and financing for projects that don't yet have customers?
That was the central question explored by our panelists; Mohamed Magdy Allam, CEO of Hassan Allam Digital Infrastructure; Lamyaa Gadelhak, partner and chair of the global project finance group at Baker McKenzie; Ahmed Sobhy, deputy CEO of eFinance Investment Group; and Maged Ezzeldin, country senior partner and deals leader at PwC Egypt.
The opportunity is substantial, but so is the price tag. Building AI infrastructure at a commercially meaningful scale requires enormous upfront investment. Allam estimates that a data center with a 20 MW IT load, equipped to accommodate the GPUs needed to train and run AI models, could cost upwards of USD 600 mn, depending on the technology deployed.
The problem? It's a chicken-and-egg situation. “To do so, you need the financing. To get the financing in place, you first need the customers — you need the agreements. To get the customers, you go back, and you need the building, the land and the product,” Allam explained.
Egypt's relatively immature data center market adds another layer of complexity. There are few local precedents for developing and financing projects of this scale, making it difficult for investors and lenders to assess the risks.
And there’s no single ingredient that guarantees success. Ezzeldin described AI infrastructure as a combination of real estate, technology, energy, connectivity, talent, cooling systems, supply chains, and regulation. “In some cases, you can have the land, but not the power. You have the power, but not the demand. You have the demand, but not the finance. You need all of the above,” he said.
Demand: The missing piece of the puzzle
Egypt's domestic market isn’t yet generating enough demand to justify large-scale AI infrastructure investment. “I think demand is probably the biggest barrier, to be transparent. I think that we do a lot of hyping of AI,” Sobhy said. While AI adoption is gaining traction, Egyptian businesses have yet to generate the level of demand for computing capacity seen in more mature markets.
But the opportunity doesn't have to be limited to Egypt. Allam argued that growing international demand for computing power, coupled with capacity constraints in the US and Europe, creates an opening for Egypt to develop infrastructure serving overseas customers.
Hassan Allam Digital Infrastructure, a partnership between Hassan Allam and A15, believes it can capitalize on that opportunity. Allam pointed to the partners’ experience delivering 100 MW of data center capacity internationally, alongside Hassan Allam’s track record in renewable energy, logistics, and desalination infrastructure.
International demand could also help unlock the domestic market. By securing large overseas customers, developers could achieve the scale needed to make computing capacity more affordable for Egyptian businesses. “On the back of demand, everything else is solvable. We’ve done it before. We think we can do it again for that sector,” Allam said.
Financing an AI data center isn't quite like financing a conventional infrastructure project. Gadelhak explained that the industry is developing multiple financing models as hyperscalers increasingly look to move costly physical infrastructure off their balance sheets.
Rather than financing everything as a single asset, developers can separate the physical data center from the technology housed inside it, allowing different components to be funded independently.
That distinction matters because different assets have very different lifespans. GPUs might have an economic life of around five years, while buildings and other physical infrastructure can remain operational considerably longer.
Gadelhak pointed to emerging GPU financing structures with tenors of approximately five years, demonstrating how technology can be financed separately from the data center itself. “Rather than reinventing the wheel when it comes to financing, I think what we need to do for Egypt, if there is the appetite of course from the lenders, is to look at how they were funded elsewhere,” she said.
Currency mismatches present another major challenge. Much of the equipment required for AI infrastructure must be imported and paid for in foreign currency, while many prospective Egyptian customers generate revenues in EGP.
Ezzeldin argued that developers need to match their funding sources to their revenues and investment requirements. Local banks could finance construction and other EGP-denominated expenses, while development finance institutions, export credit agencies, and equipment vendors could help fund foreign currency requirements. He also emphasized the importance of matching financing tenors to asset lifespans, distinguishing between long-term physical infrastructure, medium-term cooling and network equipment, and shorter-lived GPUs.
Regulation could unlock domestic demand
For Sobhy, the biggest opportunity to stimulate local demand lies with government and regulated industries. Financial institutions, payments providers, and government entities require secure, sovereign infrastructure, meaning their data and AI models need to remain in Egypt. But regulations and operating requirements that keep institutions reliant on their own on-premises infrastructure can prevent them from benefiting from shared computing capacity.
One solution is to share the infrastructure. Institutions could maintain separate, secure environments while drawing computing power from centralized facilities. A shared data center with thousands of GPUs would allow institutions to scale their computing requirements up or down, rather than each purchasing expensive equipment that might sit underutilized.
“I think one very important enabler is for government and regulated industries to say it's okay to be on the cloud and it’s okay to use the data center, as long as it’s in Egypt,” said Sobhy. He goes on to say, “what's important is that those industries will in a way subsidize the rest of the market, so you can get a lot more innovative companies. It has strong spillover effects.”
Even with customers and financing secured, developers still need access to power. Sobhy identified delays in allocating electricity capacity to suitable plots of land as a significant obstacle to getting projects off the ground. “Power allocation to the right plots of land isn't happening as quickly as it should,” he said.
Egypt nevertheless has a compelling proposition as a regional hub. Ezzeldin highlighted the country’s connectivity through submarine cables, its geographical position between continents, competitive labor and construction costs, and potential to supply data centers with renewable electricity. “Egypt's right to win, really, is, in my mind, [a] green AI compute hub. If we're able to do that, that could change the game,” he said.
But delivering on that potential will require coordination across government. AI infrastructure projects intersect with multiple authorities responsible for investment, telecommunications, land, water, and electricity. Ezzeldin suggested that a golden license mechanism could help bring these requirements together and accelerate development.
He also floated the concept of a digital embassy, drawing on Estonia's arrangement with Luxembourg, under which countries could host data infrastructure abroad through bilateral agreements that address sovereignty and resilience concerns. Such arrangements could potentially help Egypt attract international customers seeking secure computing infrastructure and disaster recovery capacity.
Regulatory attitudes are already shifting, according to Allam. Having worked in the sector since 2021, he said he has witnessed increasingly proactive engagement from the government, particularly Egypt’s Ministry of Communications and Information Technology (MCIT), in addressing regulatory barriers.
For the panelists, the takeaway was clear: Egypt doesn't lack the fundamental ingredients for a competitive AI infrastructure industry. The challenge is bringing them together — securing demand, structuring finance, allocating power, and streamlining approvals — in a way that gives investors the confidence to build at scale.
tap or click here to read the panel’s full transcript.