Siemens will connect 400 MW of power produced at the Burullus power plant to the national grid within days, Deputy Electricity Minister Sabah Mashali tells Al Mal. It brings the total output from Siemens’ three plants to 5.2 GW, from the operation of 12 units. Separately, the Electricity Holding Company is set to pay EUR 25 mn in dues to Siemens for the work it completed at the plants, a source says.