TAQA Arabia, Alcazar Energy, and FAS Energy are expected to complete each of their 50 MW solar power plants in Aswan’s Benban solar power park and link them to the national grid within two weeks, Electricity Ministry sources said. Alcazar and TAQA, a subsidiary of Qalaa Holdings, have each completed around 97% of their respective plants, while FAS is reportedly scheduled to complete its plant within the coming few days.