Tunneling operations of Cairo Metro Line 3’s phase 4A was completed at a total cost of EUR 257 mn as well as local currency portion of EGP 1.8 bn, Transport Minister Hisham Arafat said, according to Ahram Gate. Phase 4A, which is 5.15 km long and includes five stations will be for an earlier delivery than end of 2018 as had been originally expected.