Posted inENERGY

MENA renewables capacity is set to double by 2031, driven by Saudi solar

Saudi Arabia will add 60 GW of renewables capacity between 2026 and 2031 — half of everything MENA builds over the period, the International Energy Agency said in its recently released Renewables 2026 report, even as it trimmed its Saudi forecast on slow project progress. The UAE is a distant second at 13 GW and Egypt comes in a close third at 12 GW.

The larger picture: The region’s installed renewables capacity is on track to more than double to nearly 200 GW by 2031 — and most of that will come from solar. The IEA expects the region to add 122 GW of new capacity over 2026-2031, raising renewables’ share of total electricity generation from 5% to 15%. Solar is expected to account for 80% of this added capacity, the highest of any region globally.

What the Kingdom is building for is export capacity. Saudi Arabia’s Liquid Displacement Program targets 1 mn bbl / d of freed-up crude by shifting domestic power generation off liquids. That logic — hydrocarbon producers deploying renewables to free up oil and gas for export — accounts for roughly two-thirds of the IEA’s forecast regional growth, led by the Kingdom and Oman. The remaining third comes from import-dependent power systems hedging against gas price volatility, among them Egypt, Tunisia, Morocco, and Iraq.

The downward revision to the Saudi forecast sits alongside cuts elsewhere in the Gulf. The IEA also lowered Iran and Iraq on a large share of pipeline projects yet to reach final investment decision, and Oman as its hydrogen plans stalled, with two projects from earlier hydrogen rounds cancelled for lack of offtakers and others stuck pre-FID, taking the renewable capacity that would have powered them out of the forecast.

The biggest near-term risk is the war’s wobbly supply chain. Combined Chinese solar PV module imports to Saudi Arabia, the UAE, Iraq, Jordan, Iran, and Lebanon fell 61% y-o-y in 9M 2026, the IEA reports, citing disruption from the Strait of Hormuz closure. One developer told the agency that several financial closes and project-agreement signings could be delayed by six to 12 months.

On a per-capita basis, the Gulf’s smaller markets lead. The UAE overtakes Australia for the global top spot at more than 4k kWh per person by 2031, with Oman third and Qatar fifth, putting them in a new tier alongside Bulgaria, Greece, Austria, and Spain.

THE ASSUMPTIONS- The 200 GW figure is based on a reading that accounts for current policies and the current pipeline. It does not assume faster permitting, grid build-out, or financing than what’s already underway. All of that upside sits in the accelerated case. Capacity additions between 2026 and 2031 could be almost 30% higher in the IEA’s upside case — around 158 GW instead of 122 GW, taking total installed capacity to nearly 233 GW by 2031 — if grid, regulatory, and financing constraints are addressed.